The load tests, which aim to demonstrate the structural integrity of the load path, were performed two years ago through the Assembly Hall; now, they must be repeated for the path that runs through the vast crane hall above the Tokamak Building (crane rails, runway beams, structural columns and the remainder of the civil works supporting the cranes).
The commissioning activities in the crane hall will require approximately one month. At their conclusion, the cranes will return to the Assembly Hall to be equipped for a series of load tests, this time with a load that is representative of the major components to be handled during the assembly phase.
In this second phase of testing, the bridge cranes will be fitted with two 350-tonne test loads (previously used to qualify the two vacuum vessel sector sub-assembly tools), plus additional loads to reach the required weight.
REEL est fier d’avoir contribué à nouveau aux activités de Flamanville 3 en fournissant des colliers de serrage.
REEL sera présent au salon VIVA FABRICA du 23 au 26 février 2023 : gratuit et ouvert à tous, venez nous rencontrer !
Groupe REEL reprend CNIM Systèmes Industriels, qui conçoit et réalise des systèmes et composants complexes.
REEL devient la première entreprise au monde certifiée par DNV selon l’ISO 19443 !